TIN news: Construction of the new Muscat International Airport is scheduled to be completed by the end of this year, announced Oman Minister of Transport and Communications (MoTC) Dr Ahmed bin Mohammed Al Futaisi.
According to Al Futaisi, 86% of construction work was completed of the new airport last year, though 90% of it was expected to be complete as per the original plan.
The delay was a result of a number of factors, including delays made by the contractors.
According to Al Futaisi, 86% of construction work was completed of the new airport last year, though 90% of it was expected to be complete as per the original plan.
The delay was a result of a number of factors, including delays made by the contractors.
"This is to ensure the top safety standards."
After the completion of the construction, the airport will undergo a four to six month trial period, stated the minister while announcing the 2016 plans of the MoTC.
Al Futaisi was quoted by Muscatdaily.com as saying: "The basic plan this year is to at least complete all construction work. At the end of the year, we will announce when we can operate [the airport]."
The official launch date has yet not been announced as it takes almost four to six months for airlines to start operating at an airport after its construction.
Al Futaisi was quoted by Times of Oman as saying: "This is to ensure the top safety standards."
A new budget airline is expected to start operating at the airport this year.
Public Authority for Civil Aviation CEO Mohammed bin Nasser bin Ali Al Zaabi stated that almost 1,400 planes fly over the region every day.
Al Zaabi was quoted by Times of Oman as saying: "This is an increase of 19% compared to 2014."
The ministry has also commenced the construction of the Oman Rail Centre of Excellence.
Al Futaisi was quoted by Muscatdaily.com as saying: "The basic plan this year is to at least complete all construction work. At the end of the year, we will announce when we can operate [the airport]."
The official launch date has yet not been announced as it takes almost four to six months for airlines to start operating at an airport after its construction.
Al Futaisi was quoted by Times of Oman as saying: "This is to ensure the top safety standards."
A new budget airline is expected to start operating at the airport this year.
Public Authority for Civil Aviation CEO Mohammed bin Nasser bin Ali Al Zaabi stated that almost 1,400 planes fly over the region every day.
Al Zaabi was quoted by Times of Oman as saying: "This is an increase of 19% compared to 2014."
The ministry has also commenced the construction of the Oman Rail Centre of Excellence.