Hefei metro starts test running
TIN news: Testing started on the first metro line in Hefei on January 20. Initial tests are being carried out on a 1·4 km section of Line 1 at up to 80 km/h using 45 staff. Nine parameters are being tested while trains are moving and a further 27 while static.
Of the fleet of 26 trainsets ordered from Nanjing SR Puzhen Rail Transport Co, four have so far been delivered, the first on November 28. A further two are due to arrive by the end of February, with the remainder due later this year.
Full service test running is expected to begin in a few months, ahead of full opening for passenger service in September.
The 24·6 km underground Line 1 will have 26 stations, including six that will eventually offer interchange. Construction started in June 2012, following approval in January that year.
City authorities are planning an eight-line network by 2020, totalling more than 300 route-km. The north-south Line 1 and east-west Line 2 would be the main arterial routes.
Of the fleet of 26 trainsets ordered from Nanjing SR Puzhen Rail Transport Co, four have so far been delivered, the first on November 28. A further two are due to arrive by the end of February, with the remainder due later this year.
Full service test running is expected to begin in a few months, ahead of full opening for passenger service in September.
The 24·6 km underground Line 1 will have 26 stations, including six that will eventually offer interchange. Construction started in June 2012, following approval in January that year.
City authorities are planning an eight-line network by 2020, totalling more than 300 route-km. The north-south Line 1 and east-west Line 2 would be the main arterial routes.