Seymour Whyte begins work on Forty Bends upgrade project
TIN news: Work has started on the $96m arch-shaped crossing of Whites Creek at Forty Bends, located in the Blue Mountains in New South Wales, Australia.
Being carried out by Seymour Whyte under a $85m deal by New South Wales Roads and Maritime Services in last October, the upgrade forms part of the $250m realignment of the Great Western Highway between Katoomba and Lithgow.
The company has installed 50 precast concrete arches, each weighing about 20t, to complete the new 45m-long arch structure over a creek.
Being carried out by Seymour Whyte under a $85m deal by New South Wales Roads and Maritime Services in last October, the upgrade forms part of the $250m realignment of the Great Western Highway between Katoomba and Lithgow.
The company has installed 50 precast concrete arches, each weighing about 20t, to complete the new 45m-long arch structure over a creek.
"Work on the reinforced soil walls and backfilling is expected to take about 12 weeks to complete."
Australian Deputy Prime Minister and Infrastructure and Regional Development Minister Warren Truss said: "This section of highway can be dangerous during poor weather and, in winter, the road has been often closed due to black ice.
"The realignment will see 2.5km of road upgraded to a three-lane divided highway, while twin bridges over Whites Creek will be constructed, significantly improving safety and reliability."
Calare federal member John Cobb said: "The opening of the arch will allow the cold air to pass through rather than rising to the road surface, reducing the risk of black ice forming on the highway. It will also serve as a crossing for local fauna."
Under the next phase, the company will construct 18m-high reinforced soil walls above and around the arch to support the roadway embankment.
Construction of concrete pavements, rope and on-ground fauna crossings in the arch tunnel, as well as a realigned creek channel at the arch inlet, will complete the works.
"Work on the reinforced soil walls and backfilling is expected to take about 12 weeks to complete," added Cobb.
The Australian Government is fully funding the Forty Bends Upgrade, and has also committed $200m towards the Great Western Highway upgrade, while the remaining $50m is being provided by the New South Wales Government.
"The realignment will see 2.5km of road upgraded to a three-lane divided highway, while twin bridges over Whites Creek will be constructed, significantly improving safety and reliability."
Calare federal member John Cobb said: "The opening of the arch will allow the cold air to pass through rather than rising to the road surface, reducing the risk of black ice forming on the highway. It will also serve as a crossing for local fauna."
Under the next phase, the company will construct 18m-high reinforced soil walls above and around the arch to support the roadway embankment.
Construction of concrete pavements, rope and on-ground fauna crossings in the arch tunnel, as well as a realigned creek channel at the arch inlet, will complete the works.
"Work on the reinforced soil walls and backfilling is expected to take about 12 weeks to complete," added Cobb.
The Australian Government is fully funding the Forty Bends Upgrade, and has also committed $200m towards the Great Western Highway upgrade, while the remaining $50m is being provided by the New South Wales Government.