TIN news: Federal government would acquire 412 acres of land for railway container yard and construct railway line (25 kms) from sea port to Coastal Highway to Gwadar Port. According to documents available with Business Recorder, the land would be acquired for container yard measuring 1,900 X 600 meters and railway line of 25 kilometres from Gwadar Port to Gwadar railway container yard onward up to 25 kms at a point outside Gwadar limits, on Gwadar-Turbat-Hushab-Besima-Mastung rail link.
The proposed container yard will have capacity to handle about 500 railway bogie type freight wagons including marshalling of freight trains. The scope of work also includes establishment/construction of railway rest house of 3,400 square feet including allied facilities, erection of boundary stones for demarcation of acquired land and provision of logistic facilities for the required site engineer and staff.
Owing to increasing trend in land prices in Gwadar area, there is an immediate requirement for the acquisition of land for railway container yard, station other operational facilities and railway line from sea port up to coastal highway at Gwadar. The land will be kept reserved for developing of future rail link to Gwadar Port. The Central Development Working Party (CDWP) has proved this project with cost Rs 1.33 billion on August 31, 201. The original PC-1 of the project was revised and its cast increased from Rs 449.94 million to Rs 1.33 billion.
Pakistan Muslim League-Nawaz (PML-N) govt has allocated Rs 882 million in the development budget 2015-16 for this purpose. The project would be completed in two years. The original PC-1 of the project envisaging acquisition of 453 acres of land for railway container yard/station and double track line from container yard to deep sea port was approved by the CDWP in its meeting held on 25-02-2006 at the cost of Rs 450 million.
The cost of land was based on the rates furnished by the consultant at that time. Afterwards, Joint demarcation was carried out by the Pakistan Railways and Revenue Officials for the container yard and right of way up to 25 Km outside Gwadar Limit, for an area of 373 acres. The Secretary Board of Revenue, Government of Balochistan, Quetta was approached to intimate the cost of 373 acres of land, which was furnished as Rs 465 million. The approved amount of Rs 450 million was accordingly paid to Secretary (Revenue), Board of Revenue, Quetta during the year 2005-06 & 2006-07 against the demand of Rs 465 million. Gazette Notification under Section-4 of Land Acquisition Act was issued during October 2006.
Later on, a corrigendum dated 17-12-2007 was issued by EDO/Gwadar, through which the cost of land was increased to Rs 943.520 million and the area of land reduced from 373 acres to 285 acres, ie, restricting only to container yard. EDO (Revenue), Gwadar vide his letter No 434-38 dated 28-4-2008 informed that initial cost of the land amounting to Rs 450 million, furnished by Secretary Board of Revenue, Government of Balochistan is not valid, as the same was tentative and was estimated without due process. This necessitated revision of the PC-1. Now the revised cost is based on the recent mutations/sale deeds, including the cost of structures and trees etc. Commissioner, Makran Division at Turbat vide his letter No 169397/RB dated 25 June, 2010 has also provided copies of mutation showing the rates of land in the vicinity of container yard
The proposed container yard will have capacity to handle about 500 railway bogie type freight wagons including marshalling of freight trains. The scope of work also includes establishment/construction of railway rest house of 3,400 square feet including allied facilities, erection of boundary stones for demarcation of acquired land and provision of logistic facilities for the required site engineer and staff.
Owing to increasing trend in land prices in Gwadar area, there is an immediate requirement for the acquisition of land for railway container yard, station other operational facilities and railway line from sea port up to coastal highway at Gwadar. The land will be kept reserved for developing of future rail link to Gwadar Port. The Central Development Working Party (CDWP) has proved this project with cost Rs 1.33 billion on August 31, 201. The original PC-1 of the project was revised and its cast increased from Rs 449.94 million to Rs 1.33 billion.
Pakistan Muslim League-Nawaz (PML-N) govt has allocated Rs 882 million in the development budget 2015-16 for this purpose. The project would be completed in two years. The original PC-1 of the project envisaging acquisition of 453 acres of land for railway container yard/station and double track line from container yard to deep sea port was approved by the CDWP in its meeting held on 25-02-2006 at the cost of Rs 450 million.
The cost of land was based on the rates furnished by the consultant at that time. Afterwards, Joint demarcation was carried out by the Pakistan Railways and Revenue Officials for the container yard and right of way up to 25 Km outside Gwadar Limit, for an area of 373 acres. The Secretary Board of Revenue, Government of Balochistan, Quetta was approached to intimate the cost of 373 acres of land, which was furnished as Rs 465 million. The approved amount of Rs 450 million was accordingly paid to Secretary (Revenue), Board of Revenue, Quetta during the year 2005-06 & 2006-07 against the demand of Rs 465 million. Gazette Notification under Section-4 of Land Acquisition Act was issued during October 2006.
Later on, a corrigendum dated 17-12-2007 was issued by EDO/Gwadar, through which the cost of land was increased to Rs 943.520 million and the area of land reduced from 373 acres to 285 acres, ie, restricting only to container yard. EDO (Revenue), Gwadar vide his letter No 434-38 dated 28-4-2008 informed that initial cost of the land amounting to Rs 450 million, furnished by Secretary Board of Revenue, Government of Balochistan is not valid, as the same was tentative and was estimated without due process. This necessitated revision of the PC-1. Now the revised cost is based on the recent mutations/sale deeds, including the cost of structures and trees etc. Commissioner, Makran Division at Turbat vide his letter No 169397/RB dated 25 June, 2010 has also provided copies of mutation showing the rates of land in the vicinity of container yard