South Bohemia train operating contract cancelled
TIN news: Competion authority ÚOHS has cancelled the award of a KC2·25bn contract for the operation of regional passenger services on three lines in the Šumava mountains.
In April the Jihočeský regional authority had selected the GW Train Regio subsidiary of bus company ČSAD Jihotrans for the contract, which covers 1·3 million train-km/year and was to have run for 15 years from December 2016 (RG 5.15 p7). Price was the principal criterion for the selection, with GWTR’s bid of KC88/train-km undercutting Arriva (KC89·9) and national operator ČD (KC100 to 110, reduced from an initial 160). RegioJet and National Express had opted not to bid.
The regional government believed it would save KC100m/year compared to the current direct award contract with ČD. However, the incumbent appealed, claiming procedural deficiencies including inaccurate documentation. The future of the current staff was also unclear.
ÚOHS has upheld the appeal, ruling that procedural deficiencies could have influenced the selection of the winner, and citing insufficient transparency, a very low price and unresolved questions surrounding the mutual acceptance of tickets.
In April the Jihočeský regional authority had selected the GW Train Regio subsidiary of bus company ČSAD Jihotrans for the contract, which covers 1·3 million train-km/year and was to have run for 15 years from December 2016 (RG 5.15 p7). Price was the principal criterion for the selection, with GWTR’s bid of KC88/train-km undercutting Arriva (KC89·9) and national operator ČD (KC100 to 110, reduced from an initial 160). RegioJet and National Express had opted not to bid.
The regional government believed it would save KC100m/year compared to the current direct award contract with ČD. However, the incumbent appealed, claiming procedural deficiencies including inaccurate documentation. The future of the current staff was also unclear.
ÚOHS has upheld the appeal, ruling that procedural deficiencies could have influenced the selection of the winner, and citing insufficient transparency, a very low price and unresolved questions surrounding the mutual acceptance of tickets.