| News Code 58156
Copied

Coal ship queue at Australia’s Newcastle port rises to ۴۰ amid rail work

Coal ship queue at Australia’s Newcastle port rises to ۴۰ amid rail work
|
TIN news:        The shipping queue at Australia’s Newcastle port — an indicator of demand for coal exports — jumped to 40 ships this week from 30 ships a week ago as the port’s rail system shut Tuesday for three days of routine maintenance, the port authority of New South Wales said Tuesday.
 
It said 40 ships were on their way to Newcastle port to load coal exports in the next seven days at its three terminals — the BHP Billiton-operated Newcastle Coal Infrastructure Group facility and the two Port Waratah Coal Services terminals.
 
The shipping queue is the longest since the start of June and may indicate that power station customers in Asia have started another restocking cycle for the Northern Hemisphere’s summer months.
 
Another six ships were waiting off the coast of Newcastle port for a berthing slot, and six ships were already in the port taking on coal export cargoes.
 
A total of 34 ships loaded coal exports at Newcastle port in the seven-day period ended Monday, compared with 38 ships a week earlier.
 
STEADY QUEUE AT PWCS TERMINALS
 
The two coal terminals operated by the PWCS group had a combined shipping queue of 16 ships this week, up one from last week, said the Hunter Valley Coal Chain Coordinator.
 
The vessel queue for the PWCS terminals has been relatively stable at around 15-16 ships for the past five weeks, according to Newcastle port data.
 
No details were released on the shipping queue at Newcastle Coal Infrastructure Group’s terminal, but Platts estimates it is around 20 ships, up from about 15 vessels a week ago.
 
Stocks at the PWCS Carrington and Kooragang coal terminals were at 1.2 million mt Tuesday, unchanged week on week, said the Hunter Valle Coal Chain Coordinator.
 
A three-day shutdown of the Hunter Valley railway to Newcastle port started Tuesday for planned maintenance.
 
The system is due to restart for coal trains Thursday evening, said a spokesman for system operator Australian Rail Track Corp.
 
“By closing down the network and with fewer trains running, we can ensure we get the maximum amount of rail maintenance done more efficiently.
 
Above all else, it helps provide the safest possible environment for workers,” said Jonathan Vandervoort, ARTC’s executive general manager for the Hunter Valley, in a statement.
 
In a typical week, around 3 million mt of coal exports are railed to Newcastle port’s three coal terminals, but the three-day interruption to train deliveries means the terminals’ stockpiles cannot be replenished until late Thursday.
 
“These shutdowns are planned more than a year in advance to allow customers to manage their throughput and production schedules and to ensure integration across the intricately managed Hunter coal chain,” Vandervoort said.
 
The next major shutdown of the Hunter Valley corridor for coal exports is set for August 18-20, ARTC said.
 
The Hunter Valley rail corridor serves around 40 coal mines in the coal fields of New South Wales that are operated by companies including Centennial Coal, Peabody Energy, Glencore, Rio Tinto and Yancoal.
Send Comment